BANTAYAN, CEBU — Gov. Gwen Garcia leads the groundbreaking ceremony for the concreting works on 2.2475 kilometer Kabangbang–Baod road section in Brgy. Baod here.
The Capitol has set aside P37.5 million for the concreting project. The road will follow the standard provincial road measurements of 6.1 meters in width and 9 inches in cement thickness.
The governor also opened to the public the newly completed concreting works on the intersection of Kabangbang–Baod road. It measures 542 meters long, 5 meters wide, and 6 inches of cement thickness.
Capitol spent P1.6 million pesos for the project, bringing the total cost of road works here to almost P40 million.
Gov. Garcia said she will always be fond of Brgy. Baod since it is the only barangay in the entire Bantayan Island where she won during her first bid for governorship in 2004. | Mary Ann Rose Cabangbang