The Official Website of the Province of Cebu is continuously being improved to better serve every Cebuano. Some photos featured on this site are sourced from third-party contributors — proper credit is given to the original owners whenever applicable.
Substantially Completed/ PCCP = 4340 lm DL (100%)
Carcar City, Cebu
SHALOM CONSTRUCTION INCORPORATED
310 C.D/ Rev Dur 507 CD/Start June 22, 2023/Exp. April 26, 2024/Rev Exp #.1 July 31, 2024 [Due to 13 CD Time Extn #.2 ] Rev Exp #3. Nov. 9, 2024 (Due ti Adt'l. 101 CD from VO #1)
expired
₱
First warning letter issued
Status
Status
|
Plan
|
Actual
|
Plan
|
Actual
|
Previous
|
This Period
|
To Date
|
Variance %
|
|---|---|---|---|---|---|---|---|
|
6.1
|
4.34
|
6.1
|
6.1
|
99.09
|
0.02
|
99.11
|
|