Home / Bids and Awards Committee / Addendum No. 16-49: Bid Bulletin for Adv. No. 16-085 [Supply and Deliver 4,000 pieces Deformed Bars, 10mmx6.0m; 4,000 pieces Toilet Bowl, porcelain finish; and 4,000 bags Cement, 40kg/bag, pozzolan, for assistance of Toilet Construction Materials for the different barangays and municipalities of Cebu Province]

Addendum No. 16-49: Bid Bulletin for Adv. No. 16-085 [Supply and Deliver 4,000 pieces Deformed Bars, 10mmx6.0m; 4,000 pieces Toilet Bowl, porcelain finish; and 4,000 bags Cement, 40kg/bag, pozzolan, for assistance of Toilet Construction Materials for the different barangays and municipalities of Cebu Province]

Posted on by: marimar_2009

Cebu Provincial Government logo

Republic of the Philippines
PROVINCE OF CEBU
BIDS AND AWARDS COMMITTEE
Cebu Capitol, Cebu City

SUPPLEMENTAL / BID BULLETIN

 

 

ADDENDUM NO.  16 – 49

 

 

For:    Adv. No. 16-085 –       Supply and Deliver 4,000 pieces Deformed Bars, 10mmx6.0m; 4,000

pieces Toilet Bowl, porcelain finish; and 4,000 bags Cement, 40kg/bag, pozzolan, for assistance of Toilet Construction Materials for the different barangays and municipalities of Cebu Province.

 

 

This addendum is issued to modify or amend items in the Bid Documents for the procurement of the different projects of the Province of Cebu, as listed.  This shall form an integral part of the Bid Documents.

 

  • SCHEDULE OF PROCUREMENT OF ACTIVITIES:

FROM:                                                  TO:

4.  Deadline Submission of Bids October 26, 2016, Wednesday, 10:00 A.M. NOVEMBER 2, 2016, Wednesday,
      Opening of Bids 10:00 A.M.
5.  Bid Evaluation / Determination of LCB October 26, 2016 November 2, 2016
6.  Post-Qualification November 2, 2016 November 9, 2016
7.  Preparation of BAC Recommendation of Award November 4, 2016 November 11, 2016
     Approval of Resolution of Award & NOA November 7, 2016 November 14, 2016
     Receipt of approved Notice of Award November 9, 2016 November 16, 2016
      Contract preparation November 11, 2016 November 18, 2016
8.   Request for SP Authority Not required. Project is specifically described & details thereof are sufficiently provided in the APP. Not required. Project is specifically described & details thereof are sufficiently provided in the APP.
      Approval of SP Authority
9.   Contract Signing November 16, 2016 November 26, 2016
10. Issuance of Notice to Proceed November 18, 2016 November 28, 2016

 

For guidance and information of all concerned.

 

Cebu Capitol, Cebu City, October 13, 2016.

 

 

(sgd)  ATTY. MARK C. TOLENTINO

Chairman

 

Conformed:

 

______________________________________

(Signature over printed name)

 

______________________________________

(Name of Company)

 

Date: _____________________________________

 

 

 

**Please acknowledge receipt hereof by re-sending this through Telefax No. (32) 253-9614, duly signed received.**

 

 

 

 

 